Rsams
Mechanical
- Mar 7, 2011
- 2
I need to make several connections to existing(new)pipe stubs on a Co2 refrigeration skid. welds will be multiple pass fillet socket weld. pipe to flange. All pipe is carbon A106 and flanges are the same. Class #300. Process C02 is at -35f during operation. My question is are there any welding procedures that need to be adhered to because of the low Temperature? Is there a certain alloy tig rod needed? any pre or post heating needed? etc.
Thanks in advance.
Thanks in advance.