RobsVette
Mechanical
- Apr 15, 2009
- 94
Hi everyone,
I have a question regarding a welding procedure qualification.
Recently, we performed a repair on a boiler tube that was slighly less than 3/16" diameter. However, our welding procedure only qualifies us down to 3/16" because we originally qualified the procedure using a 1/2" piece of plate. Under normal circumstances I would just weld the procedure on a .375" piece of plate and do teh required bend and tensile tests.
However, the material here is SA-335 Grade P91. So all I have access to is the original piece of pipe that was welded. This is a 1.25" OD x .179" thickness piece of tubing. Is there any way I can use this piece of tubing to qualify a new procedure for the correct diameter? I looked through the usual spots in section IX but the answer is not apparent.
Thanks in advance for any help.
Rob
I have a question regarding a welding procedure qualification.
Recently, we performed a repair on a boiler tube that was slighly less than 3/16" diameter. However, our welding procedure only qualifies us down to 3/16" because we originally qualified the procedure using a 1/2" piece of plate. Under normal circumstances I would just weld the procedure on a .375" piece of plate and do teh required bend and tensile tests.
However, the material here is SA-335 Grade P91. So all I have access to is the original piece of pipe that was welded. This is a 1.25" OD x .179" thickness piece of tubing. Is there any way I can use this piece of tubing to qualify a new procedure for the correct diameter? I looked through the usual spots in section IX but the answer is not apparent.
Thanks in advance for any help.
Rob