Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Welding progression uphill / downhill in Sec IX

Status
Not open for further replies.

Konrad

Mechanical
May 20, 2002
84
Hello,
The question is whether it's enough to qualify a PQR for both uphill and downhill when a welder makes one continous bead all around the pipe in 6G without stopping? May seem strange, but I found no clarification about it.

Konrad
 
Replies continue below

Recommended for you

Position is a supplementary variable. If you are performing impacts, vertical up matters.
 
As a secondary consideration, progression up vs. down, is an essential variable for welder qualification, so, if you're trying to get both a PQR and a WPQ with one test, review the rules for welder qualification in QW 350.
 
Actually in my case one WPQ=one PQR. The shop is small and only one welder makes code production, so each time I make a qualification for him, I always make procedure and performance on the same samples. I'm using GTAW and GMAW.
Say, the sample is 25mm OD tube and the welder makes three GTAW welds in G6, all round without stopping. I can make 4 samples for bending out of first of three welds. This will give one sample from top, one from bottom, one uphill and one downhill. The second and third weld will go to full section tensile testing. Is this enough to have both uphill and downhill qualified?

Konrad
 
Konrad,
Since you are needing a WPQ, you must test for both uphill and downhill progression. In your case, you may be covered, just be sure you have the proper number of bend coupons representing each progression.
 
Weldtek,
This is exactly my concern: QW-356 lists "progression" as a variable. But QW-302.3, QW-452.1(a), nor QW-463.2(d) does not say that the opposite specimens have to be the same progression. Is there some requirement saying so?

Konrad
 
Weldtek,
Let me explain my problem more percisely. Is there somewhere in Sec. IX written:
one uphill qualification=4 uphill specimens,
one dowhill qualification=4 downhill specimens,
one uphill+downhill qualification=4uh+4dh specimens?

Isn't it enough to have 2 uphill and 2 downhill specimens from one weld acc. to QW-463.2(d) ?

Konrad
 
Konrad,
Since progression is an essential variable for welder qualification, a test assembly is required to represent each of those conditions. If it were plate and two coupons were required, you would need two coupons with uphill progression and two with downhill progression. When testing a welder on pipe, if four coupons are required, you would need four for each progression.
I'm not aware of a paragraph which spells this requirement out, but, the key is QW351 'a welder shall be requalified whenever a change is made in one or more essential variables'
 
I woud not run PWR and WPQ on pipe, I would do separate,
Plate for PQR and pipe for WPQ, regardless of savings,
I am small too and have many procedures.
when you want to save too much, it is no good. I have lots of experiency on that.
I used top save a lot, at the end it is not worth the effort.

genb
 
Thanks guys. I'm not just trying to do it or defend it. I'm trying to eliminate it and just was not sure. I think you're right.

Konrad
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor