PipeLayer15
Mechanical
- Jun 24, 2020
- 2
I am working for a mechanical contractor that is constructing B31.1 power piping. Butt welds, max 16" sch40 pipe (majority <8"), design P/T of 232psig @ 250'F.
Owner's specification is asking for 20% VT examination of all root passes and 100% RT examination of all completed welds.
What is the value in completing the root pass examination? Is there any value to the owner that we would be asking them to concede if we request to have the root pass examination waived and/or removed from the contract by change order?
If it matters, the welder is very competent and has a very low failure rate. Assumed that the only value proposition to the contractor is to catch something on the root pass inspection and deal without before completing the weld and incurring the RT cost. This is of low concern to us.
Industry feedback is greatly appreciated.
Owner's specification is asking for 20% VT examination of all root passes and 100% RT examination of all completed welds.
What is the value in completing the root pass examination? Is there any value to the owner that we would be asking them to concede if we request to have the root pass examination waived and/or removed from the contract by change order?
If it matters, the welder is very competent and has a very low failure rate. Assumed that the only value proposition to the contractor is to catch something on the root pass inspection and deal without before completing the weld and incurring the RT cost. This is of low concern to us.
Industry feedback is greatly appreciated.