jropert
Structural
- May 18, 2010
- 23
I had a question regarding the effects and possible requirements of welding to existing wide flange beams while these beams are under load.
This particular job requires cutting holes into an existing concrete floor slab, which is currently supported by wide flange beams (no metal deck; this is an older building). My company and I are not the EOR, but are the contractors in charge of constructing this project. The given structural drawings call for added steel beams and channels to frame around the new openings in the floor slab (there will be relatively light mechanical units and floor drains supported by this framing). These are indicated to be welded to the existing wide flange beams of the floor structure.
My question is this: The structural drawings don't call for any special shoring to be put in place prior to welding to the existing wide flange beams. This isn't unusual for this type of application from what I've seen in past projects (at least at my previous employment with a structural consulting company). However, I am not sure if it should be automatically implied that we as the contractor are responsible to figure out shoring requirements during the welding process (btw, this floor is 30 feet above the ground floor). The concern is that by welding the shear connection tabs to the existing beams, this will "weaken" the localized area while the beam is still under floor load.
Does anyone have some commentary, code requirements, guidelines, etc. for this situation? I can't imagine that this is a unique situation, but don't really know the best place to look.
Thanks,
Josh R
This particular job requires cutting holes into an existing concrete floor slab, which is currently supported by wide flange beams (no metal deck; this is an older building). My company and I are not the EOR, but are the contractors in charge of constructing this project. The given structural drawings call for added steel beams and channels to frame around the new openings in the floor slab (there will be relatively light mechanical units and floor drains supported by this framing). These are indicated to be welded to the existing wide flange beams of the floor structure.
My question is this: The structural drawings don't call for any special shoring to be put in place prior to welding to the existing wide flange beams. This isn't unusual for this type of application from what I've seen in past projects (at least at my previous employment with a structural consulting company). However, I am not sure if it should be automatically implied that we as the contractor are responsible to figure out shoring requirements during the welding process (btw, this floor is 30 feet above the ground floor). The concern is that by welding the shear connection tabs to the existing beams, this will "weaken" the localized area while the beam is still under floor load.
Does anyone have some commentary, code requirements, guidelines, etc. for this situation? I can't imagine that this is a unique situation, but don't really know the best place to look.
Thanks,
Josh R