Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations The Obturator on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

What is the general thing to do for a construction on landslide area

ITsSB

Structural
May 6, 2022
31
I have an existing structure (belt conveyors and its pier and footings, both steel and RC). It transports materials from downstream (near river) on a very steep slope. Previous geotech investigation found out that top layer is basaltic and the lower one is conglomerate. Their conclusion is there is a landslide. As a solution we are considering
1. provide drainage so that there is less surface water entering.
2. apply grouting under existing piers and provide new piers with piles deep beyond the stable point for the support of this new concrete piers. (intermediate points)
3. provide pile retaining at lower and intermediate points as part of lateral support.
We are yet to hear from our Geotechnical Engineer. I now its a complex topic but what other general solutions should we consider/expect.
 
Replies continue below

Recommended for you

What do you mean 'there is a landslide'? Like there is a landslide risk?

Google slope stability measures, there are many. Soil nails, drainage, re grading the slope, retaining walls. Not much more detail can be given with so little information
 

Part and Inventory Search

Sponsor