jdeebaba
Civil/Environmental
- Feb 15, 2012
- 7
HI I am using HECRAS and I want to model the river channel between the two dams. For the upstream I have 1 minute flow data and also for downstream I have 1 minute flow and stage data. I tried to input the data in the HECRAS model for 5 months. I have a huge data set. However, I cannot increase the data limit in HECRAS. The maximum number of ordinates that I could use in HECRAS seems to be 10000. Would you give me any suggestions on how to do the simulation ?
Thanks.
Thanks.