Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

When to backfill a foundation?? 1

Status
Not open for further replies.

tocida

Electrical
Apr 2, 2003
1
After a foundation wall is poured what is the recommended time frame before backfilling?
 
Replies continue below

Recommended for you

You should get 70% of your 28 day strength in about 14 days. It depends how high you're backfilling also but I would say a minimum of 14 days.
 
It also depends on how the wall was designed. If it is a cantilever wall you may be correct. However, if it is a restrained wall and utilizes the slab above for support, I wouldn't recommend backfilling until the upper slab is in place and has reqached specified strength.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor