RFreund
Structural
- Aug 14, 2010
- 1,885
Let's say you have a renovation project which requires an existing beam to be supported while you remove a column, or something along these lines. If you put demolition drawings together or even if you don't - I would think that you would call out for the beam to be shored. You might even provide a reaction or design load. You may even require that the shoring design be delegated to the contractor and even require it to be stamped. I suppose you could go so far as to design the shoring. Or you could just show the final condition and chalk up the shoring of the beam as means and methods. I'm curious to know how far do you typically go? Is there a technically correct answer to this? If you delegate this design or leave it up to the contractor do they need to have an engineer design the temporary shoring?
EIT
EIT