birddogger
Electrical
- Feb 23, 2004
- 31
I have a client who is trying to "cut fat" from a project, and one item they are proposing is moving some of the larger loads on their system from the main distribution switchboard (where breaker "real estate" is much higher) to a downstream distribution panel. We're talking a couple of 400A loads more suited to a robust 3000A 277/480V switchboard than what's basically a wall-mounted 1200A I-Line panel that we were ear-marking for more localized loads. The distance from the load to either of the two boards is about the same, so they're pressing to feed them from the I-Line panel.
Can it be done? Yeah. Is it good engineering practice? No. As a rule of thumb, big loads go on big switchboards and smaller loads go on smaller boards/panels. But I can't really figure out a way to explain why other than the standard "that's just the way it's always been done around here" response. Any suggestions as to how to make my point?
Can it be done? Yeah. Is it good engineering practice? No. As a rule of thumb, big loads go on big switchboards and smaller loads go on smaller boards/panels. But I can't really figure out a way to explain why other than the standard "that's just the way it's always been done around here" response. Any suggestions as to how to make my point?