debgallery
Civil/Environmental
- Aug 20, 2007
- 25
Here's the scenario:
36" CMP (maybe 20 years old or more) conveys a creek under a parking lot (FEMA 100-year flow =358-cfs). The CMP runs through a drop manhole so as to avoid water and sewer mains that run through the parking lot(about 4' drop - currently getting the survey done). The total length of pipe is about 150' and the elevation difference between the inlet and the outlet is about 14.5'. There is a tall embankment on the downstream side of the parking lot that failed this spring, crushing the outlet. At the time it was not possible to actually inspect the culvert because the water was too high but the manhole had actually moved and you could see that there are void spaces around the manhole. We also can't even find the outlet to the pipe but there is water flowing out of the debris. I'm working on getting it video'd.
We've been hired to come up with alternatives to fix this thing temporarily because the whole site is being redeveloped. Obviously, alternative 1 is to replace the whole thing with an appropriately sized system.
Here's my question: If we proposed rehabilitating the pipe with a CIPP or other liner is there anyway to stabilize the bed material or the obvious voids around the MH so that piping does not continue? Also, is it even possible to use CIPP or other liner with a drop manhole?
Thanks, any thoughts are appreciated
36" CMP (maybe 20 years old or more) conveys a creek under a parking lot (FEMA 100-year flow =358-cfs). The CMP runs through a drop manhole so as to avoid water and sewer mains that run through the parking lot(about 4' drop - currently getting the survey done). The total length of pipe is about 150' and the elevation difference between the inlet and the outlet is about 14.5'. There is a tall embankment on the downstream side of the parking lot that failed this spring, crushing the outlet. At the time it was not possible to actually inspect the culvert because the water was too high but the manhole had actually moved and you could see that there are void spaces around the manhole. We also can't even find the outlet to the pipe but there is water flowing out of the debris. I'm working on getting it video'd.
We've been hired to come up with alternatives to fix this thing temporarily because the whole site is being redeveloped. Obviously, alternative 1 is to replace the whole thing with an appropriately sized system.
Here's my question: If we proposed rehabilitating the pipe with a CIPP or other liner is there anyway to stabilize the bed material or the obvious voids around the MH so that piping does not continue? Also, is it even possible to use CIPP or other liner with a drop manhole?
Thanks, any thoughts are appreciated