cubexco
Computer
- Jan 23, 2006
- 6
Hello,
I have a 60'x35' 1.5" composite metal deck slab on which we have screwed 5/8" PEX pipes for Radiant Heating.
The decking is supported on approx 18' steel bar joists 4' O.C. The Joists bear on 15' girders.
A 6"x6" WWF is placed over the pipes. The mesh is clipped/screwed to the deck at various overlap joints to prevent it from bucking up too high.
The slab thickness is 4", which would place the mesh at 1"-1.5" under the slab surface.
The County Bldg Inspector refused to allow this, stating that the mesh cannot be over the pipe or cannot touch it.
I showed him a fax from the PEX manufacturer stating that this configuration was acceptable. He wants me to obtain a sealed letter from the EOR stating this configuration is ok.
I have 2 questions:
1. Putting the mesh under the pipe means the mesh would be 2.5" below the surface, Wouldn't that negate the purpose of the mesh?
2. Should I have the contractor cut control joints on this slab?
Thanks!
Nik
I have a 60'x35' 1.5" composite metal deck slab on which we have screwed 5/8" PEX pipes for Radiant Heating.
The decking is supported on approx 18' steel bar joists 4' O.C. The Joists bear on 15' girders.
A 6"x6" WWF is placed over the pipes. The mesh is clipped/screwed to the deck at various overlap joints to prevent it from bucking up too high.
The slab thickness is 4", which would place the mesh at 1"-1.5" under the slab surface.
The County Bldg Inspector refused to allow this, stating that the mesh cannot be over the pipe or cannot touch it.
I showed him a fax from the PEX manufacturer stating that this configuration was acceptable. He wants me to obtain a sealed letter from the EOR stating this configuration is ok.
I have 2 questions:
1. Putting the mesh under the pipe means the mesh would be 2.5" below the surface, Wouldn't that negate the purpose of the mesh?
2. Should I have the contractor cut control joints on this slab?
Thanks!
Nik