youssef91
Structural
- Nov 3, 2003
- 14
G.C. wants to install a 3x nailer on the top of w10x steel beam at the field, the provisions were not to drill in the moment frame top flange or web, G.C. suggests to install a shop weld steel plate 1/4" x 3 1/2" x 8" @16" o.c. at the side of top flange and use lag screws for nailer attachment as a replacement for welded studs at top flange.
Any help would be greatly appreciated.
Any help would be greatly appreciated.