bookowski
Structural
- Aug 29, 2010
- 983
Have some questions regarding design of wood shoring. Particular situation is a wood framed building (joists into masonry walls) that was vacant for 30yrs and is in very bad shape. 100% of the joists are being replaced in sections. The contractor wants to provide temporary stud walls to shore the joists during this work.
A few questions for this situation and in general:
- Studs will be unsheathed. If I provide a row of mid-height blocking along the wall and diagonal nailed 2x braced at each end of the wall can I consider all studs braced at mid-height in the weak direction?
- In reality the shoring walls will see little load, we are not jacking anything up. They are there in case one or more sections of floor fails during the course of work. Are there any references/guides as to a design approach. I've started off by assuming the shoring walls are the only supports, i.e. all joists at all levels come out of their pockets while sustaining a construction load at each floor (5 floors by the way). That obviously works, but is it too conservative?
- The plan is to reframe from top down in sections once shoring is in. This means that as soon as the work starts the shoring will be removed top down as they go and see less and less load. Duration factor for something like this - 1.15?
Just wondering if I'm being too conservative - it's a load of material for something that will start coming down almost as soon as it is complete. Any good shoring design books out there?
A few questions for this situation and in general:
- Studs will be unsheathed. If I provide a row of mid-height blocking along the wall and diagonal nailed 2x braced at each end of the wall can I consider all studs braced at mid-height in the weak direction?
- In reality the shoring walls will see little load, we are not jacking anything up. They are there in case one or more sections of floor fails during the course of work. Are there any references/guides as to a design approach. I've started off by assuming the shoring walls are the only supports, i.e. all joists at all levels come out of their pockets while sustaining a construction load at each floor (5 floors by the way). That obviously works, but is it too conservative?
- The plan is to reframe from top down in sections once shoring is in. This means that as soon as the work starts the shoring will be removed top down as they go and see less and less load. Duration factor for something like this - 1.15?
Just wondering if I'm being too conservative - it's a load of material for something that will start coming down almost as soon as it is complete. Any good shoring design books out there?