stevey
Structural
- Feb 19, 2003
- 11
After tensioning tendons for a large bridge project we received reports of radial cracking appearing in numerous steel anchor wedges. Some wedges only had one crack, some had multiple cracks. The cracks are visible on the exposed ends, and run from the inside diameter to the outside diameter, and I assume they continue longitudinally into the body of the wedge. No slippage has evidently occurred in the strands (verified by measurement of the strand ends), and we don't know when the cracks first occurred - no one was paying attention all last week while the tensioning was performed, and the cracks were first noted on Monday.
We have conflicting information on the seriousness of this problem. This is second-hand on my part, but I was informed that the P/T installation manual from the Post-Tensioning Institute says that these types of cracks "frequently" occur. No mention is made of what "frequently" means as a percentage of the total project. Or, what action, if any, needs to be taken.
Other (maybe) perinent information: The strands were being stressed with a short stroke jack; the duct voids will all be grouted after the final post-tensioning.
Question 1: If the voids are grouted after post-tensioning, do the (cracked) wedges actually perform any function after the grout has set?
Question 2: If the wedges are actually required, do the cracks make any difference to the future performance of the structure?
Question 3: What percentage of cracked wedges is acceptable before they should be replaced?
Our initial reaction is to replace the cracked wedges, but we are wary of construction claims.
Thanks for any help.
Steve
Steve R. Yates
City of Portland Oregon
Office of Transportation Engineering
We have conflicting information on the seriousness of this problem. This is second-hand on my part, but I was informed that the P/T installation manual from the Post-Tensioning Institute says that these types of cracks "frequently" occur. No mention is made of what "frequently" means as a percentage of the total project. Or, what action, if any, needs to be taken.
Other (maybe) perinent information: The strands were being stressed with a short stroke jack; the duct voids will all be grouted after the final post-tensioning.
Question 1: If the voids are grouted after post-tensioning, do the (cracked) wedges actually perform any function after the grout has set?
Question 2: If the wedges are actually required, do the cracks make any difference to the future performance of the structure?
Question 3: What percentage of cracked wedges is acceptable before they should be replaced?
Our initial reaction is to replace the cracked wedges, but we are wary of construction claims.
Thanks for any help.
Steve
Steve R. Yates
City of Portland Oregon
Office of Transportation Engineering