Hi,
I was wondering if anyone might be able to help me. I'm quite new to this ms project. Recently i received a project file from my colleague. He has created the GANTT chart and everything. In that file, I can see that it actually shows date from Jun05 to Mar06. Is it doable if i just want to see only dates from jan06 to Mar06? and print it out only for those periods of time.
Thank you very much in advance
I was wondering if anyone might be able to help me. I'm quite new to this ms project. Recently i received a project file from my colleague. He has created the GANTT chart and everything. In that file, I can see that it actually shows date from Jun05 to Mar06. Is it doable if i just want to see only dates from jan06 to Mar06? and print it out only for those periods of time.
Thank you very much in advance