Despy
Structural
- Feb 9, 2007
- 14
I am looking for some help on reinforcing existing wood beams. This particular problem crops up from time to time and I need a good way to address it. If you have a wood beam in an existing structure that needs to be reinforced to carry increased loads it is relatively easy to add a steel plate (or channel) to the side of the existing member. Determining the new capacity of the composite beam is a matter of relative stiffness and has been addressed elsewhere in these forums.
My question is about the mechanical connection requirements between the two pieces. To me it seems there are two cases:
1. The side plate extends over the supports.
2. The side plates stop short of the supports. This is more common since the supports are frequently inaccessable.
In the first case the load sharing is complete and the bolts/nails/screws holding the two pieces together only have to transfer the appropriate percentage of vertical applied load to the side plate (basically a flitch beam).
In the second case it seems that the bolts/nails/screws have to resist an additional component since the side plate does not reach the supports. Is it correct to calculate this additional force as the tension/compression resulting from the moment in the side plate?
Ex: A side plate carries 6000-lb*in from the moment at the center span of a uniformly loaded beam. Bolts connecting the two members are in two rows 4" apart. Thus both the upper bolt row and the lower bolt row must each carry an additional 6000/4 = 1500# in a direction parallel to the length of the beam.
Thoughts?
My question is about the mechanical connection requirements between the two pieces. To me it seems there are two cases:
1. The side plate extends over the supports.
2. The side plates stop short of the supports. This is more common since the supports are frequently inaccessable.
In the first case the load sharing is complete and the bolts/nails/screws holding the two pieces together only have to transfer the appropriate percentage of vertical applied load to the side plate (basically a flitch beam).
In the second case it seems that the bolts/nails/screws have to resist an additional component since the side plate does not reach the supports. Is it correct to calculate this additional force as the tension/compression resulting from the moment in the side plate?
Ex: A side plate carries 6000-lb*in from the moment at the center span of a uniformly loaded beam. Bolts connecting the two members are in two rows 4" apart. Thus both the upper bolt row and the lower bolt row must each carry an additional 6000/4 = 1500# in a direction parallel to the length of the beam.
Thoughts?