Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

MS Project Resource % 2

Status
Not open for further replies.

GrahamCrackers

Aerospace
Mar 26, 2007
1
When I need to change a finish date to a later date, MS Project recalculates the number of Task Hours. I didn't want them to change. How do I stop this automatic recalculation?

Thanks
GrahamCrackers
 
Replies continue below

Recommended for you

Have you tried baselining?

TTFN

Eng-Tips Policies FAQ731-376


 
You need to turn off automatic calculation. Go to Tools, Options, Calculation tab and uncheck the "Updating task status updates resource status" check box.
 
I don't believe either of these answers will produce the response you are looking for.

If you have a task set up for 40 hours worth of work over 10 days, and you need to adjust the finish date so that it now spans 15 days, but you do not want the effor or Work number to change, what you need to do is:
1. Change Type to Fixed Work - this will hold the work number fixed.
2. Update the Duration until your Finish dates is accurate.

Hope this helps!

J Black
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor