newbuilder
Structural
- Jul 1, 1999
- 73
I have a project which calls for a 100mm screed to be placed over a strucutral slab. The screed will used by forklifts etc and the design strength is to be 50MPa. The spec recommends that it is placed in two layers with mesh reinfrcement.
Are there any definitive guidelines: from what i've found, the mesh would be near to the top of the top layer with suitable cover to control early thermal drying cracks. The mix could be a 1:3 cement :10mm max agregate mix and we are considering two 50mm layers to build the 100mm screed. We will use a system of joints.
I have seen a few screed failures and the resaons were mix design and workmanship. Anybody have and views or advice regarding the above or joint layout curing times etc.?
Thanks NB
Are there any definitive guidelines: from what i've found, the mesh would be near to the top of the top layer with suitable cover to control early thermal drying cracks. The mix could be a 1:3 cement :10mm max agregate mix and we are considering two 50mm layers to build the 100mm screed. We will use a system of joints.
I have seen a few screed failures and the resaons were mix design and workmanship. Anybody have and views or advice regarding the above or joint layout curing times etc.?
Thanks NB