Zzzer
Structural
- Jun 27, 2018
- 6
I am designing a slab-on-ground with piers because of deep fill and wondering what its load transfer mechanism is like.
Can anyone please tell me if I need to design it as a suspended slab-beam on piers system?
If so, it looks like I need massive amount of piers. Let's say the beam sizes are 300mm x 600mm, slab thickness is 100mm and pier diameter is 300mm. With 250kPa end bearing capacity, the max spacing of beams is around 1.2 meters only. As I have seen many structural plans by others using 2-3meters spacing with piers in natural clay (which I assume to be 250kPa end bearing max) so I am very confused.
Thanks in advanced.
Can anyone please tell me if I need to design it as a suspended slab-beam on piers system?
If so, it looks like I need massive amount of piers. Let's say the beam sizes are 300mm x 600mm, slab thickness is 100mm and pier diameter is 300mm. With 250kPa end bearing capacity, the max spacing of beams is around 1.2 meters only. As I have seen many structural plans by others using 2-3meters spacing with piers in natural clay (which I assume to be 250kPa end bearing max) so I am very confused.
Thanks in advanced.