Loki2
Civil/Environmental
- Feb 24, 2003
- 2
Though originally a geological engineer, I now practice in the environmental field, and as such, my foundation and soils engineering knowledge is now somewhat faded... so in the hopes of getting some sage advice, here is my foundation rehabilititation issue:
We purchased (at a great price!) a post-war 24'X30' bungalow with a lean to it -- 6" lower along one side. We have dug a few test pits and found that the problem appears to be differential settling due to: 1) no footings at base of perimeter wall (crawlspace, no basement), and 2) about 2/3 of the perimeter wall base sitting on a clayey/peaty lens, versus a fine dry sandy strata under the 1/3 that has settled minimally.
We are considering, given that there is no footing, of jacking both house and the concrete perimeter wall up as a unit. We are looking at jack points every 6-8', strategically under supporting beams and existing cracks in the wall. The plan is to dig down from the outside of the house at the jack points, pre-pour jack pads, raise the wall to the desired level, then pour footings under the remainder of the wall.
I have two questions for you experts:
1) If anyone has experience with this particular strategy of jacking house and wall as a unit, please comment on your success or failure, give any advice for strategies.
2) Given the clay soil conditions, a one-story woodframe bungalow with asphalt shingle roof, and the settlement history of 6", what are the opinions out there of a desirable footing design? We do not intend to put a second story on the structure, and just want to find a cost-effective solution to this problem. I can do more detailed sizing calculations myself, but really want more your ideas of options we could consider.
Thanks very much!
We purchased (at a great price!) a post-war 24'X30' bungalow with a lean to it -- 6" lower along one side. We have dug a few test pits and found that the problem appears to be differential settling due to: 1) no footings at base of perimeter wall (crawlspace, no basement), and 2) about 2/3 of the perimeter wall base sitting on a clayey/peaty lens, versus a fine dry sandy strata under the 1/3 that has settled minimally.
We are considering, given that there is no footing, of jacking both house and the concrete perimeter wall up as a unit. We are looking at jack points every 6-8', strategically under supporting beams and existing cracks in the wall. The plan is to dig down from the outside of the house at the jack points, pre-pour jack pads, raise the wall to the desired level, then pour footings under the remainder of the wall.
I have two questions for you experts:
1) If anyone has experience with this particular strategy of jacking house and wall as a unit, please comment on your success or failure, give any advice for strategies.
2) Given the clay soil conditions, a one-story woodframe bungalow with asphalt shingle roof, and the settlement history of 6", what are the opinions out there of a desirable footing design? We do not intend to put a second story on the structure, and just want to find a cost-effective solution to this problem. I can do more detailed sizing calculations myself, but really want more your ideas of options we could consider.
Thanks very much!