C4Reactor
Chemical
- Sep 29, 2001
- 21
One of the major concern for Turnaround scheduling is the late issuance of Work Permit. Someday, esp during the beginning of the Turnaround, some work can only begin after 10:00 in the AM (Normal shift started at 7:00 AM). One way suggested is to lengthen the validity of selected non critical permits (excluding vessel entry,welding works) from 12 hours to say, 3 days. Another is to have the night shift people to prepare the WP based on earlier prepared list.
Happy to learn your experience in handling this issue.
Thanks!