Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Timber Beam Upgrade - Welded Splice Connection - FIre Hazard??

Status
Not open for further replies.

adurbin

Structural
Feb 18, 2002
20
Here's my problem, I have an existing facility that needs to reinforce its existing 6" x 12" timber beams due to failure. My proposed method is to attach steel channel shapes along the sides and bolt (6) at various locations and fasten at the ends with angles. However, the contractor building the project has indicted that he needs a spliced conneciton for the channels. The current 20'-0" length is impossible to fit in the building's current geometry. My spliced design as of know has a plate attached to both ends of the channels and welded all around. My concern is that when welding the heat buildup on the steel could could cause the wood to catch fire? Is this possible and are their preventative measure to be taken? This has to be a field weld and not a shop weld. My other option is to have a bolted spliced connection, but this is also quite difficult.
 
Replies continue below

Recommended for you

Since a channel's strength comes from it's flanges, can you bolt flange splices top and bottom?

Or, can the steel be welded prior to fitting up to the wood beams?
 
Well, after talking to the contractor -- No field welding at all. so my only option it to go to an all bolted connection. Thanks ---
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor