I have a number of sites that have a small generator (with day tank) and a small modular non-heated building(4mx4mx4m) both have their own concrete foundation that sits on frost heave insulation. My contractor wants to run a number of 100 diameter electrical conduits through the insulation. Most literature I have read says to prevent cold bridge in frost heave insulation:
1. Has anybody dealt with this in the past? What rational did you use?
2. How many penetrations is too many?
Thanks
I have a number of sites that have a small generator (with day tank) and a small modular non-heated building(4mx4mx4m) both have their own concrete foundation that sits on frost heave insulation. My contractor wants to run a number of 100 diameter electrical conduits through the insulation. Most literature I have read says to prevent cold bridge in frost heave insulation:
1. Has anybody dealt with this in the past? What rational did you use?
2. How many penetrations is too many?