Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME VIII-1: Tubesheet extended as a flange (Type BEU Heat Exchanger) calculation 6

Status
Not open for further replies.

FPPE

Mechanical
Mar 4, 2022
170
Dears,

We did the calculation of a tubesheet extended as a flange to the outside diameter of the mating flanges of shell and channel.
Now, considering the tubesheet not extended we obtain higher bending stress. How is this possible?
The hinge point is the gasket reaction diameter (that is the same of the extended configuration)and the flanged extension has no bolts load.

Please explain in accordance with UHX, I cannot find a reason for this.

One of the possible solutions (in order to satisfy all checks required by the Code) is to consider the weld overlay thickness in design calc (Inconel 625), with thicknesses as follow:

tubesheet_i20sl7.jpg


In this case I have considered 122 mm as tubesheet thickness (excluding W.O. thickness in the minimum thickness at center of tubesheet). Base material is SA 765 Gr. II. According to UCL-23 (c) and UCL-11 could I consider the cladding thickness (if it is a weld overlay)?

UCL-23:

"(c) Base Material with Corrosion Resistant Integral or
Weld Metal Overlay Cladding With Credit for Cladding
Thickness. When the base material with corrosion resistant
integral cladding conforms to one of the specifications
listed in UCL-11(a), or consists of an acceptable
base material with corrosion resistant weld metal overlay
and the joints are completed by depositing corrosion resisting
weld metal over the weld in the base material to
restore the cladding
[N.D.R.: in what sense "to restore the cladding"? We have done a weld overlay on a new forging in SA 765 Gr. II], the design calculations may be based
on a thickness equal to the nominal thickness of the base
material plus Sc/Sb times the nominal thickness of the
cladding after any allowance provided for corrosion has
been deducted, where
Sb = maximum allowable stress value for the base material
at the design temperature
Sc = maximum allowable stress value for the integral
cladding at the design temperature, or for corrosion
resistant weld metal overlay cladding, that of the
wrought material whose chemistry most closely approximates
that of the cladding, at the design
temperature
Where Sc is greater than Sb , the multiplier Sc/Sb shall
be taken equal to unity. The maximum allowable stress
value shall be that given for the base material referenced
in Table UCS-23, UF-6, or UHT-23 and listed in Section II,
Part D, Subpart 1, Table 1A. Vessels in which the cladding
is included in the computation of required thickness shall
not be constructed for internal pressure under the provisions
of Table UW-12, column (c).
The thickness of the corrosion resistant weld metal
overlay cladding deposited by manual processes shall
be verified by electrical or mechanical means. One examination
shall be made for every head, shell course, or any
other pressure-retaining component for each welding
process used. The location of examinations shall be chosen
by the Inspector except that, when the Inspector
has been duly notified in advance and cannot be present
or otherwise make the selection, the fabricator may exercise
his own judgment in selecting the locations."


UCL-11:

"(a) Clad material used in constructions in which the design
calculations are based on the total thickness including
cladding [see UCL-23(c)] shall conform to one of the
following specifications:
(1) SA-263, Stainless Chromium Steel‐Clad Plate
(2) SA-264, Stainless Chromium–Nickel Steel‐Clad
Plate
(3) SA-265, Nickel and Nickel‐Base Alloy‐Clad Steel
Plate [N.D.R.: I think that these specifications are not applicable to our weld overlay in Inconel 625 because these covers plate]
In addition to the above, weld metal overlay cladding
may be used as defined in this Part.

(b) Base material with corrosion resistant integral or
weld metal overlay cladding used in constructions in
which the design calculations are based on the base material
thickness, exclusive of the thickness of the cladding
material, may consist of any base material satisfying the
requirements of UCL-10 and any metallic corrosion resistant
integral or weld metal overlay cladding material of
weldable quality that in the judgment of the user is suitable
for the intended service.
(c) Base material with corrosion resistant integral cladding
in which any part of the cladding is included in the
design calculations, as permitted in UCL-23(c), shall show
a minimum shear strength of 20,000 psi (140 MPa) when
tested in the manner described in the clad plate specification.
One shear test shall be made on each such clad plate
as rolled, and the results shall be reported on the material
test report.
When the composite thickness of the clad material is
3/4 in. (19 mm) or less, and/or when the cladding metal
thickness is nominally 0.075 in. (1.9 mm) or less, the
“Bond Strength” test, as described in SA-263, SA-264, or
SA-265, may be used in lieu of the bond “Shear Strength”
test to fulfill the criteria for acceptable minimum shear
strength, except that the bend test specimen shall be
11/2 in. (38 mm) wide by not more than 3/4 in. (19 mm)
in thickness and shall be bent, at room temperature,
through an angle of 180 deg to the bend diameter provided
for in the material specifications applicable to the
backing metal. The results of the “Bond Strength” test
shall be reported on the material test report.
(d) A shear or bond strength test is not required for
weld metal overlay cladding.

(e) When any part of the cladding thickness is specified
as an allowance for corrosion, such added thickness shall
be removed before mill tension tests are made. When corrosion
of the cladding is not expected, no part of the cladding
need be removed before testing, even though excess
thickness seems to have been provided or is available as
corrosion allowance.
(f) Base material with corrosion-resistant integral
cladding in which any part of the cladding is included in
the design calculations, as permitted in UCL-23(c), that
is constructed of multiple cladding plates welded together
prior to being bonded to the base material shall have the
cladding-alloy-to-cladding-alloy welding that is performed
prior to bonding to the base material
(1) performed by a Manufacturer holding a Certificate
of Authorization.
(2) radiographically examined for its full length in
the manner prescribed in UW-51. In place of radiographic
examination, welds may be ultrasonically examined for
their full length (see UW-53).
(3) be supplied with a Partial Data Report if that
welding is not performed by the vessel Manufacturer."


At design temperature Sc is higher than Sb, so Sc/Sb=1. Can I consider 137 mm as thickness? Considering all the attached paragraph, is it possible to consider the weld overlay thickness ad resistant thickness?

Why, considering the higher value of "A" as specified in Figure UHX-12, we obtain lower bending stress? Why the tubesheet portion out of the external gasket diameter contributes to tubesheet strength?

Thanks in advance
 
Replies continue below

Recommended for you

Someone could help please?
 
Why a tubesheet extended as a flange?

Regards
 
r6155, to facilitate the execution of the hydrostatic test. See TEMA RCB-11.8
 
Can you send us a general drawing?

Regards
 
FPPE - I believe what you're referring to as a "tubesheet extended as a flange" is considered a full-diameter tubesheet under API660. This is required by API660 for B type TEMA front ends (bonnets), in order to maintain your gasket seal btw the tubesheet & shell girth flange when you pull your bonnet off for maintenance. You will need to thread at least 25% of your tubesheet bolt holes (min. of 4 bolt holes) to match your stud threads in order to keep your tubesheet-to-shell gasket seated when you pull the bonnet off.

As for your question on tubesheet bending stress differences btw confined tubesheet vs full-diameter tubesheet, I'd like to dig into this. Not 100% certain off top of my head, but my guess is the full-diameter tubesheet is credited for some bending resistance under the UHX calcs by accounting for the tubesheet material beyond the OD of the tubesheet bending hinge point/gasket reaction diameter.

As for your tubesheet WOL question, typically this is not accounted for in the tubesheet thickness under UHX calcs. WOL thickness is typically only treated as a corrosion allowance.
 
I have seen WOL used as part of the thickness, but ...
There was extensive X-ray and UT inspection (like 100%),
and the material thickness was only credited at the lower strength of the two materials.
In most cases it isn't worth the time and effort.

= = = = = = = = = = = = = = = = = = = =
P.E. Metallurgy, consulting work welcomed
 
I can't see the advantage of the extended tubesheet because once the studs are loosened the gasket has to be replaced.
I consider a test ring for the shell side shop hydrostatic test. This test ring shall be shipped with the complete exchanger.

Regards
 
As explained by Krausen above if you use collar bolts or tapped holes for every 4th bolt hole in your tubesheet you can remove the channel without decompressing the shell gasket.


-Christine
 
BUT: You have to install full bolting to do the shell side hydro!

Had some fun conversions with the clients on this.

"If you could hydro on 25% bolting, the other 75% WOULDN'T BE THERE".

LOL

Regards

Mike

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
EdStainless, exactly, we made 100% UT on tubesheet and we have considered the allowable of the base material (since the WO allowable is higher, as explained in my post). Thanks for your answer.
 
Do you mean that the pressure stays on the shell side when the bonnet is removed? And with only 25% of the collar studs?.

Regards
 
No. A feature of BEU type exchangers with full dia tubesheers is that a shell side hydro may be performed with the channel (or bonnet) removed, exposing the tube field for observation. All bolting must be installed.

The 25% collar studs or tapped holes are only to prevent the shell-tubesheet gasket from becoming unseated when the bonnet is removed.

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Reuse of gasket is not recommended (see ASME PCC-1), therefore, the use of collar stud does not make sense.

Regards
 
r6155, the gasket shell-tubesheet is not removed, so it is not reused.
 
The current gasket has lost its original characteristics.

Experience has clearly shown that only a new gasket will reliably provide the necessary plastic deformation and elastic recovery characteristicsessential to achieve an effective seal.

Regards
 
FPPE said:
Why the tubesheet portion out of the external gasket diameter contributes to tubesheet strength?

The loading imposed by the bolting moment on the extended tubesheet acting as a flange is in the opposite direction of the bending caused by the pressure inside the shell on the tubesheet.
 
Experience has clearly shown that only a new gasket will reliably provide the necessary plastic deformation and elastic recovery characteristicsessential to achieve an effective seal.

A new gasket will be more reliable than keeping the original shellside gasket in-service, but this does not mean the in-service gasket is unreliable. My understanding is the shellside gasket will remain undisturbed providing the collar bolts tension is checked before and during the loosening of the balance of the bolting. This is the sole purpose of the collar bolts.
 
FPPE,

It is very straightforward. By para UCL -11, SA 765 Grade II doesn't qualify for total thickness. Therefore, thickness to consider is 127 mm. Your design thickness for calculation will be 127 mm (nominal thickness) as Sc/Sb=1.

On the bending stress question, we haven't seen your calculation procedures and therefore, can't advise on it.

By the way, why did you put that M20 screws at the top of the tubesheet? Is it to lock the flange bolts?

GDD
Canada
 
The M20 threaded hole is very useful for lifting the tubesheet during machining

Regards

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor