Hello guys, I was wondering about the removal of formwork and shoring. I look up on ACI 318:2019 and they only mention to look it up on ACI 347, and so I did and found this (image above)
Does this mean that if I have a beam with a 7 m span where live load > dead load, then the formwork and shoring should only be release after 21 days?
Thank you