sajk14
Mechanical
- Sep 2, 2009
- 56
Hello All,
API 653 section 9.4 states that the shell can be repaired by 'deposition of weld metal'.
My query is that if weld deposition repairs are carried out on the shell, what rules should be used with regards to minimum weld spacing requirements?
I would typically use the guidance shown in Figure 9.1 in API 653. However someone has challenged me on this stating that Fig 9.1 only applies to shell insert plate repairs or shell patch plate repairs, therefore we don't need to apply these rules as API 653 does not specifically refer you to Fig 9.1 for weld deposition repairs.
The location of the first weld overlay repair is just above the 'shell to bottom' connection and the other is located right next to a vertical shell butt joint.
I would appreciate your thoughts and opinions on the above.
Many Thanks
API 653 section 9.4 states that the shell can be repaired by 'deposition of weld metal'.
My query is that if weld deposition repairs are carried out on the shell, what rules should be used with regards to minimum weld spacing requirements?
I would typically use the guidance shown in Figure 9.1 in API 653. However someone has challenged me on this stating that Fig 9.1 only applies to shell insert plate repairs or shell patch plate repairs, therefore we don't need to apply these rules as API 653 does not specifically refer you to Fig 9.1 for weld deposition repairs.
The location of the first weld overlay repair is just above the 'shell to bottom' connection and the other is located right next to a vertical shell butt joint.
I would appreciate your thoughts and opinions on the above.
Many Thanks