CivilCon99
Civil/Environmental
- Jan 10, 2024
- 1
A geotechnical investigations was conducted prior to a bridge replacement project. Two soil borings were completed to bedrock on each side of the stream. The borings only showed free water and no 24hr reading was conducted (due to drilling in the roadway). The free water in the borings showed 5 feet less than normal stream elevation and below the new abutment foundations. During construction of the new abutments adjacent to the river, the contractor encountered water at or above stream elevation. The contractor is seeking a site differing condition claim stating the geotech logs showed free water deeper than their foundations and that they did not plan for enclosed cofferdams and heavy dewatering during construction.
1.) Is the free water in the borings strong enough data for a differing site conditions claim?
2.) Regardless of the geotech report findings, shouldn’t the contractor have to expect water at least at stream level during excavation adjacent to the river and bid/build accordingly?
1.) Is the free water in the borings strong enough data for a differing site conditions claim?
2.) Regardless of the geotech report findings, shouldn’t the contractor have to expect water at least at stream level during excavation adjacent to the river and bid/build accordingly?