Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Earth fill and Compaction under a Septic Leach field

Status
Not open for further replies.

zahid106

Civil/Environmental
Nov 3, 2000
16
I need to place about ten feet of fill to bring the site up to grade and install a septic leach field.
Are any specific compaction requirements/procedures for the backfills under aleach field?
 
Replies continue below

Recommended for you

If you are placing fill beneath the future leach field, you may need to use sand for a few feet beneath the field. What do the local laws say?
 

Local laws do not have specific guidance on the compaction of backfilled soils below the leach field.
 
Sometimes, you are required to perform the grading, and then conduct your percolation test. Depending on the fill material, you might be able to compact to a lesser amount than structural fill.

It will all be a function of the soil composition, compaction, and depth of fill. If the fill soil has more sand, you will have higher flow rates than in clay. Compaction to 85 percent will have higher flow rate than 95 percent. That kind of thing. You probably don't want to conduct lab testing on the permeability of the fill material at different densities to determine the target compaction, that will get costly.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor