Krausen
Mechanical
- Jan 1, 2013
- 267
Curious forum's opinion on minimum girth weld & branch weld spacing requirements on new piping & modified existing piping (B31.3 code)?
Most companies have best practices/standards that define minimum weld spacing clearances for girth & branch welds for new piping. However, I'm not 100% sure this is a B31.3 code requirement (similar to Section VIII for pressure vessel design).
I have some applications with both carbon steel (P-1) & stainless steel (P-8) piping where modifications are being proposed on existing piping to weld new small-bore branch welds onto existing girth welds. Mostly for installing new low point drains & high point vents in tight spaces.
The existing piping is modern carbon steel(A106-B pipe)& modern stainless steel(A312-TP316 pipe).
The piping would typically not be designed new this way, but the question has come up on if we can still modify the existing piping this way to retrofit these small bore branch welds.
Most companies have best practices/standards that define minimum weld spacing clearances for girth & branch welds for new piping. However, I'm not 100% sure this is a B31.3 code requirement (similar to Section VIII for pressure vessel design).
I have some applications with both carbon steel (P-1) & stainless steel (P-8) piping where modifications are being proposed on existing piping to weld new small-bore branch welds onto existing girth welds. Mostly for installing new low point drains & high point vents in tight spaces.
The existing piping is modern carbon steel(A106-B pipe)& modern stainless steel(A312-TP316 pipe).
The piping would typically not be designed new this way, but the question has come up on if we can still modify the existing piping this way to retrofit these small bore branch welds.