Dear,
How to prepare construction programme under the same contract with different phases and completion dates. The programme should have multiple critical paths,one for each phase. Or else only one critical path to the latest completion date would not reflect the truth.
Previously, I use Microsoft Project subprojects for each phase and combined them into one called master, but I am not sure this method is correct or not. Please advise.
Regards,
Gary Lo