Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Construction project with different phases under the same contract

Status
Not open for further replies.

e74222

Civil/Environmental
Oct 9, 2009
3
Dear,

How to prepare construction programme under the same contract with different phases and completion dates. The programme should have multiple critical paths,one for each phase. Or else only one critical path to the latest completion date would not reflect the truth.

Previously, I use Microsoft Project subprojects for each phase and combined them into one called master, but I am not sure this method is correct or not. Please advise.


Regards,


Gary Lo
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor