Elimelech
Bioengineer
- Sep 18, 2024
- 1
Hey everyone,
I’m using MS Project 2016 Desktop and I want to ensure that tasks are scheduled to run only on consecutive working days. For example, if I have a 4-day task that is set to start on a Wednesday, I want it to be automatically postponed to the following Monday, rather than split across Wednesday, Thursday, Friday, and Monday.
I’d like this rule to apply to both weekends and holidays.
Does anyone know how to set this up?
I’m using MS Project 2016 Desktop and I want to ensure that tasks are scheduled to run only on consecutive working days. For example, if I have a 4-day task that is set to start on a Wednesday, I want it to be automatically postponed to the following Monday, rather than split across Wednesday, Thursday, Friday, and Monday.
I’d like this rule to apply to both weekends and holidays.
Does anyone know how to set this up?