dec4trax
Geotechnical
- Apr 22, 2002
- 7
Contractor is trenching approx 8 ft thru random fill, placing bedding, 3 ft re-concrete pipe, and compacted granular backfill (#8).
Invert of pipe is critical. We have now encountered some very soft soil (STP=woh) along the trench alignment below the random fill at the bottom of the trench. Contractor reports that pipe in this area settled 3 inches overnight based on a lazer sighting. Before continuing the trench line, we want to adjust the installation procedures to minimize (prevent) settlement. Does anyone know any tricks of the trade that pipe contractors use when they encounter this situation? Our contractor has suggested using timber/cribbing or concrete in the trench to spread the load ?? Any suggestions are welcome. Thanks !!
Invert of pipe is critical. We have now encountered some very soft soil (STP=woh) along the trench alignment below the random fill at the bottom of the trench. Contractor reports that pipe in this area settled 3 inches overnight based on a lazer sighting. Before continuing the trench line, we want to adjust the installation procedures to minimize (prevent) settlement. Does anyone know any tricks of the trade that pipe contractors use when they encounter this situation? Our contractor has suggested using timber/cribbing or concrete in the trench to spread the load ?? Any suggestions are welcome. Thanks !!