Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Foundation design on 1:1 slope

Status
Not open for further replies.

pbtyler

Civil/Environmental
Jul 10, 2003
1
I am the low man on the totem pole among many who have their hats in the ring on this project (geotechnical engineer, structurual engineer, foundation engineering contractor, city building inspector, geologist.) Many competing ideas.

The site is a 1:1 ascending slope composed of bedrock (with 1-4 feet of silty sand overlaying the bedrock. The bedrock is composed of slate, hard to moderately hard, folded and contorted. There is a lack of consistent structural planes of weakness. Height of the slope is 45-50 feet. Length of the site is 85'.

Preliminary design idea is to obtain concrete box of roughly 30 x 20 x 10 feet for basement, with additional height of 8' for first floor living area. Structure would then support two more stories of wood framing of same square footage (~600 sq. ft.) To obtain this, slope would be cut 32-34' for length and 22' depth. Rear retaining wall would be ~18 feet.

Geo report indicates that vertical cut slope may be excavated up to 12', and after that temporary shoring required.

Any ideas on most practical and economic way to get a 30x20x18 concrete box into the slope?



 
Replies continue below

Recommended for you

Warning: I am an amateur.

If the "bedrock" is stable, chances are you could bring in one of those wheel trenchers and cut a footer trench. Pour concrete directly into the trench, having it mechanically lock itself to the walls.

Sounds like plenty of backfill. Investigate "geofoam" to minimize the soil hydraulics.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor