Structural
- Dec 19, 2018
- 51
CRSI Design Guide for Pile Caps shows a minimum embedment of pile into the pile cap by 4 inches, and then the bottom reinforcements are to have 75mm concrete cover above pile head.
Is this valid for concrete piles or is this just for steel piles? I do not see the need to have 75mm extra cover for reinforcement when the pile head is also concrete.
The CRSI handbook does have a statement about this, but it's not a very clear statement whether concrete piles need extra cover on top.

Can pile cap reinforcements be laid directly on top of the concrete pile head? If not, how much spacer is required?
Is this valid for concrete piles or is this just for steel piles? I do not see the need to have 75mm extra cover for reinforcement when the pile head is also concrete.

The CRSI handbook does have a statement about this, but it's not a very clear statement whether concrete piles need extra cover on top.

Can pile cap reinforcements be laid directly on top of the concrete pile head? If not, how much spacer is required?