    Corbel condition for Tension Nuc/shear Vu not more than 1

    Dear Experts As per ACI 318-08 code , there is a condition for using the equation for the corbel design as follow " section R11.8.1 ,an upper limit is provided for Nuc because this method of design has only been validated experimentally for Nuc less than or equal to Vu , including Nuc equal to...
  2. h-badawy

    Design of non-ductile steel elements on the seismic overstrength factor

    Thank u driftlimiter Actually i read ASCE 7- chapter12 and AISC341 as well , but i did not find any items speak clearly about the design of brittle elements such as steel connections , base connection , strut , bracing ,..etc.,. Only section 12.10.2 and the writer speak about the collector...
  3. h-badawy

    Design of non-ductile steel elements on the seismic overstrength factor

    Dear experts For the seismic design category (C ,D & E ),where is the provision/section in the code (ASCE OR AISC) discuss/describe the design of non-ductile elements like connections, base connections, bracing ,…etc., on the overstrength factor.and also is there any exception we can consider...
  4. h-badawy

    Splice connection of cantilever steel beam rested on / supported by steel beam

    Dear experts I have little bit difficult connection for slopped cantilever steel beam rested on a steel beam , the slop of 2% is required by Arch. Engineer for the roof drainage . I make a sketch (see attached)of a proposal connection of the two beams and i need your opinion about it. Thank...
  5. h-badawy

    Base connection between existing concrete column and cantilever steel girder

    Thank you all for your useful ideas, and appreciated your support. Thank you
  6. h-badawy

    Base connection between existing concrete column and cantilever steel girder

    You mean the bottom flange of all the cantilever and back span girder with the perpendicular girder will be welded with base plate ? Thank you
  7. h-badawy

    Base connection between existing concrete column and cantilever steel girder

    JoshPlum and pham Actually i have the as-built drawings and I don’t have any problems with safety of the concrete columns and footings . In any case the arch. Needs to raise the height of the shed for 1.5m more ,so i will cut the existing anchors and chip 1 m from top of the concrete columns to...
  8. h-badawy

    Base connection between existing concrete column and cantilever steel girder

    Dear experts I have an issue in the site, the client wants to upgrade a steel shed for gas station to a modern one. The structural system of the existing shed now is space truss rested on concrete columns (6m height)spacing between four columns are 10m x10m , the new one will be simple girder...
  9. h-badawy

    Connection detail of two reversed columns between floors

    I don’t want to make this connection, i am a design reviewer for this project and the designer use this column as frame resisting system in the lower floor in Y-direction and cantilever for 4m parapet height in X-direction. I am try to convince him to rotate the column in the lower level and...
  10. h-badawy

    Connection detail of two reversed columns between floors

    Thank you dik Yes i know that is not practically, and i agree with you in this regard but i want to make a small exercise to prove this issue to the designer, but i didn’t not find any source for such a connection. Thank you
  11. h-badawy

    Connection detail of two reversed columns between floors

    Dear experts Can I connect two columns in different orientation between two floors as below sketch, and if it could be done , what is the appropriate detail connection of this case?. Thank you Thank you
  12. h-badawy

    Minimum design wind load

    I mean, these minimum values shall be applied to all elements , for example if the windward and leeward are both lesser than the minimum i have to increase both of them to be 16psf. I feel the total pressure on the building will be too much especially for steel building. Thank you
  13. h-badawy

    Minimum design wind load

    Greetings, As per ASCE7-10 section28.4.4 , the minimum design wind load shall be 0.77 kN/m2 for wall and 0.38 KN/m2 for slab , my question, is the value of P=q *( GCpf - GCpi) shall calculate for each each wind exposed element ( leeward, windward , end zones , side pressure,…….etc) and then...
  14. h-badawy

    Allowable of TDS in the groundwater used in soil compaction before construction

    Dear experts I am a client engineer, and i got letter from the contractor that he wants to use the source of water ground table in the soil compaction, and i have a doubt in the quantity of total dissolved solid and Cl And Sulfate in this water ,in the other hand the client need a prof from any...
  15. h-badawy

    Assign time history for blast load

    Greetings, I need any paper or lectures summaries the steps of assign blast load by time history in etabs. Thnx Thank you