Thanks.
Not sure about the standard but they mentioned primary reason to select steel trap(STM) gasket is due to Significantly lower minimum gasket seating stress.
Hello,
For HRSG drum manhole, our spec. calls for spiral wound gasket vs our supplier came back with deviation to use steel trap (STM) gaskets. I have not heard but is that allowable?
Thanks in advance.
wcaseyharman (Electrical)
Further to your reply in above thread.
for 300 MW Steam turbine Generator;
We plan for
3 CTs for each phase on line side (total 9 CTs)
3 CTS for each phase on neutral side (total 9 CTs)
Now customer is asking to keep
3 CTs for each phase on line side (total 9 CTs)
4...
I have general question. On Steam turbine LP section, I have typically seen rupture discs for the protection from the over pressurization. In a new project, ACC, Air Cooled Condenser supplier is providing Rupture discs covering the Steam turbine LP portion volume as well. In this case, can we...
wcaseyharman (Electrical)
Thanks.
We are in the early design phase with the Generator supplier so protection and metering design is not done.
I am not Generator/Elect. expert.
So can anyone advise me best way to proceed, i.e. how many Total CTs on line side(per phase) and how many Total CTs on...
cranky108 (Electrical
Thanks.
wcaseyharman (Electrical)
Thanks.
stevenal (Electrical)
Thanks. 3 CTs per each phase so total 9 for line side. Same way 3CTs per each phase on Neutral side so total 9 for Neutral side.
edison123 (Electrical).
Thanks. You replied as "Normal set up is one line CT...
For a large Steam turbine Generator (300 MW class), any preference for dedicated current transformers for each phase vs multi core current transformers?
i.e. One multi core CT on line and One multi core on Neutral side vs 9 on line side and 9 on Neutral side.
Any suggestion?
Thanks in advance !
For a large Steam turbine Generator (300 MW class), any preference for dedicated current transformers for each phase vs multi core current transformers?
i.e. One multi core CT on line and One multi core on Neutral side vs 9 on line side and 9 on Neutral side.
Any suggestion?
Thanks in advance !
I have a question about Steam turbine performance test code (ASME PTC 6 vs DIN1943).
I am not familiar with DIN. We do not have contractual requirement to follow one over the other.
1.If OEM prefers DIN, would it be possible to accept? what are the fundamental difference and risk vs benefit...
Hello
Any tips to prevent potential water leak to Air circuit in TEWAC (Totally Enclosed Water Air Cooler) Turbine Generator?
Having only one leak detector in the heat exchanger is reliable?
Thanks in advance !
I have a quick question regarding scope of Vacuum breaker valve. who should be technically providing it? Steam turbine supplier or Condenser supplier? and what is the reason for that?
Thanks in advance