  1. piper1982

    Separation distance between process units in Petroleum Refinery. Mitigation measures!

    GD2, Allow me to answer your questions. Point 4:- Yes OISD Guidelines are mandatory. Its required for all oil and gad projects in India. Point 5:- The plot plan has to be approved by the petroleum authority of India (PESO - https://peso.gov.in/web/home)or else it wont be insured and...
  2. piper1982

    Separation distance between process units in Petroleum Refinery. Mitigation measures!

    Thank you for valuable insights. The concern was raised to client during preliminary discussions on plot plan. The client/PMC are simply washing their hands off the issue and requesting the detail engineering contractor to resolve the issue. Ironically the FEED was done by the same company who...
  3. piper1982

    Separation distance between process units in Petroleum Refinery. Mitigation measures!

    We are working on a Hydrocracker project located in India. The code to be followed is OISD (Oil industry safety directorate). As per the code separation distance between adjacent process units needs to be 36 meter considering 6 meter wide road between the units. The distance of process unit must...
  4. piper1982

    Material Identification

    Dear Prady22, The isometric which has been shared has lot of information missing. Is this the same isometric which was Issued for construction and is being used for redlining now for additional work. An IFC isometric must have Piping material specification, Fluid code, temperature, pressure...
  5. piper1982

    LNG Fundamentals

    Apologies cappoxy, Refer the link below. Thankshttp://files.engineering.com/getfile.aspx?folder=606c105a-6a4d-4942-871a-aeef239004b1&file=GIGNL.pdf
  6. piper1982

    LNG Fundamentals

    Hello Cappoxy, GIGNL documents would be a good place to start. Refer the attached documents. Thankshttp://files.engineering.com/getfile.aspx?folder=e3142990-e967-402a-9acf-59487e8ea590&file=LNG_6_-_Safeguard_systems_7.3.09-AAcomments-Aug09.pdf
  7. piper1982

    Derated Flange

    Hello Guys, The question arose, after one of the instrumentation guy came to us (Piping) with a specification in which vendor was providing derated flanges with the package instead of standard flanges. Thanks for your valuable Feedback.
  8. piper1982

    Derated Flange

    Hi, What is a derated flange, what are its applications. Tried googling the topic, but did not get satisfactory results. Have gone through ASME 16.5, but couldn't find the answer. Thanks for your help.