It appears what it boils down to is being technically competitent enough to review the drawings and make the minor modifications versus actually being in responsible charge design of the project (which was completed before I started here like I mentioned). I certainly don't want to be stealing...
A few things to I should clarify on this subject:
1. I am under no pressure from my boss (also a licensed PE, but not overly familiar with the ins/outs of the project) to stamp the drawings. Just a suggestion that he made. Our city ordinance (might also be state/federal law) requires all...
I am a licensed PE working for a municipality. We have roughly 90% drawings for a street reconstruction and stormwater separation project, which need some minor adjustments prior to being put out to bid. I've been asked by my boss to make the minor adjustments to the design and stamp the...