Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Search results for query: *

  1. majesus

    Primary Fuse Voltage rating on Wye-Wye vs Delta-Wye XFMRS

    All, to further add to my question. On Cooper Eaton online fuse program, it also gives me VLN rated primary fuses for Wye Wye and VLL fuses for Delta-Wye. Not sure why for Wye-Wye you only need VLN rated fuses, how about internal phase to phase short circuit scenarios? Hopefully someone can...
  2. majesus

    Primary Fuse Voltage rating on Wye-Wye vs Delta-Wye XFMRS

    All, I'm working on a project where the client has already purchased two 33kV/480V Wye-Wye transformers, one at 1.5MVA the other at 1MVA. Both Wye neutrals are solidly grounded. These transformers come with current limiting, primary fuses mounted within the transformer's cable box enclosure...
  3. majesus

    Meggering a load bank, different values when bonding frame

    Just across the frame. We didn't have the opportunity to investigate further. Just a weird but interesting problem. Vendor took the unit back today. Wanted to post it here if anyone seen something similar.
  4. majesus

    Meggering a load bank, different values when bonding frame

    All, Unusual problem that I can't explain, looking for some help: We have a 480V, 3phase, 2MW resistor load bank for testing generators. If we megger the phases with respect to the frame, with the unit's frame not bonded, we get high MegaOhms on all phases. If we then bond the frame, and...
  5. majesus

    Typical Cost for Decommissioning and Removal of O/H transmission lines.

    At a mine site, runs along a roadside. Flat terrain, in semi-arid environment with easy access. In mid-Southern USA, no Florida swamps. Double circuit, 795MCM ACSR, strung on both sides of steel lattice structure. Removal of structure and conductors. Foundation can stay, however, possible to...
  6. majesus

    Typical Cost for Decommissioning and Removal of O/H transmission lines.

    I am trying to find a unit cost for decommissioning and removing of O/H transmission lines. 2016 PG&E Final Generator Interconnection Unit Cost Guide has the following: Double Circuit (per mile, $x1000) 69kV = 420 115kV = 420 230kV = 650 Those published values seems high for removal of lines...
  7. majesus

    Dedicated ground fault protection for all feeders on a LV solidy ground system

    We are designing a 480V solidly grounded system for an industrial mine located in the Southern USA, where the climate is mild and the area will be designed with a solid industrial ground grid with multiple ground rods. Customer has requested that all 480V branch circuit feeder (15A CB and...
  8. majesus

    Installing two different voltage rated one a parallel run feeder

    Hi Waross, Thanks for the reply. The run will be 305m. I simulated the circuit in PSIM and I can live with the % of unequal current sharing. This will not be an issue. The question in regards to code violate under the CEC. The CEC states for parallel runs: a) free of splices throughout the...
  9. majesus

    Installing two different voltage rated one a parallel run feeder

    Sorry, I messed up the title grammer and did not notice until after posting. Too bad there is no way to go back and edit after clicking submit.
  10. majesus

    Installing two different voltage rated one a parallel run feeder

    At a site in Canada, we have a 5kv feeder that has four 3c-#500 MCM, shielded, Aluminum armoured, 5kV, 100% cables running in parallel. The run length is 350m. One of the phases on a cable failed and the client wants to replace it. They already have onsite a 400m reel of 3c-#500MCM, shielded...
  11. majesus

    Why do PT fuses have internal resistance?

    Curiosity question: for PT primary fuses, say 4160V, current limiting, ferrule mounting similar to the fuses shown in the following specification sheet: Link I noticed that when I measure the fuse resistance with an ohm meter I usually get around 30ohms for a good, non-blown fuse. For all other...
  12. majesus

    Seperate Grounds for Metal-Oxide Surge Arrestors on Poles?

    Thanks Stevenal, My original post was a question about isolating the arrestor from a switch mat bonded to a ground grid to avoid step-touch potentials. I was focused on this topic that I did not realize you were discussing the fact that the arrestor's terminal leads also includes the ground...
  13. majesus

    Seperate Grounds for Metal-Oxide Surge Arrestors on Poles?

    Thanks for responding Stevenal, but you misunderstood the question. The arrestors are located on top of the power pole and the 69kV EPR cable's termination is connected to the arrestor's line side terminal as close as physically possible. The arrestor's ground lug is connected directly to a...
  14. majesus

    Seperate Grounds for Metal-Oxide Surge Arrestors on Poles?

    Hello, We are installing a 69kV EPR incoming service cable from O/H lines to feed our plant. At the O/H power pole structure there is a 3 phase disconnect switch gang operated by a lever handle at ground level. The power pole is wood and sits in a steel pile. There are three ground rods, a #4/0...
  15. majesus

    oil filled transformer data

    Venture here: http://www.eaton.com/Electrical/Consultants/ConsultingApplicationGuide/idcplg?IdcService=GET_FILE&RevisionSelectionMethod=LatestReleased&Rendition=Primary&dDocName=TB08104003E]Eaton Info[/url] And go to page 105 in the pdf.
  16. majesus

    Measuring the Resistance from XFMR's NEUT to GND on a NGR system

    Morning Waross, The NGR is located inside the dry type unit sub. Measurements must be done the system is off. We plan to de-energize and shall try the multi-meter. Just out of curiousity... Assuming the neutral on secondary of the unit sub XFMR was floating and the system was artificially...
  17. majesus

    Measuring the Resistance from XFMR's NEUT to GND on a NGR system

    We have a 3 wire, 600V secondary distribution fed from a 1.5MVA XFMR with a 5A NGR on the Neutral to ground. The system is designed to Alarm on Ground fault only. Yesterday while clearing snow with the excavator, the crew ran over a 600V, 3c-#4/0 armoured cable feeding the fresh water pump...
  18. majesus

    Reuse a step up Delta-Wye XFMR for a step down Wye-Delta application?

    Zigzags do not have to be as close as possible. (Unlike surge arrestors.) As you know, Zigzags are used to establish a ground point so that we can monitor ground faults on the system. They and are not required in extreme proximity to the main XFMR.
  19. majesus

    Reuse a step up Delta-Wye XFMR for a step down Wye-Delta application?

    It is commonly done like this. It provides an easy way of connecting the Zigzag onto the system. Also notes that the Canadian Electrical Mines Act requires that the Zigzag Circuit breaker be monitored and if it disconnects, it must de-energize the system. (This is not shown on my SLD.)
  20. majesus

    Reuse a step up Delta-Wye XFMR for a step down Wye-Delta application?

    Thanks Waross, I knew you would answer ;) I appreciate your help. This is an industrial off the grid site. The 4kV system should be well balanced. The Wye-Delta XFMR has a Z=5.8%, also to note it is an oil type, 3 phase XFMR. It shall be wired for temperature monitoring. I do not have a true...
Back
Top