Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. ogbuehi

    Adding a Knock Out to an Existing Panel - Does it Void UL Listing?

    I've always wondered this as well. I have seen some panels with 60+ circuit breakers. It just seems that if a knockout was punched for every CB, the box might not be structurally sound anymore.
  2. ogbuehi

    Transformer costs

    Thanks dpc. I just need ballpark numbers.
  3. ogbuehi

    Transformer costs

    I normally would, but I'm in a very austere location and don't have an easy means contacting vendors. As for the enclosure, it can be IP equivalent. Just as long as it's rated for outdoor use.
  4. ogbuehi

    Transformer costs

    Whoops!! This is a distribution transformer but I made a typo. It should be a 630kVA and not 6030kVA[surprise]. So I'm calculating 877A on the low side.
  5. ogbuehi

    Transformer costs

    I believe I posted this in the wrong forum previously. I've been trying to get cost estimates for a transformer. Specifications for the transformer are as follows: outdoor rated (NEMA appropriate enclosure), 630kVA, 50Hz, 11kV(delta)-415V/240V(wye), pad-mounted, oil-filled. Shipping or...
  6. ogbuehi

    Transformer costs

    Does anybody have a good source to determine the cost to purchase a 6030kVA/11kV-415V/50Hz, outdoor rated transformer? I don't have access to my RS means. Thanks in advance.
  7. ogbuehi

    Dual position transformer

    I was afraid to ask as well. The load has protection but based on what I'm seeing, that means the cables from the high side of the XFMR back to the switchgear at the power plant has none. I'm having the contractor get the configuration of the transformer. We can't measure the voltage at the...
  8. ogbuehi

    Dual position transformer

    That would mean that the transformer is expecting a wye voltage on the high side. But there are only 3 cables on the input side of the transformer. Does that mean that not connecting the neutral to the high/wye side of the transformer has no affect?
  9. ogbuehi

    What is the purpose of anchoring a transformer that weighs 15,000lbs?

    The reasoning I would think that you anchor the transformers down is because of minor vibrations, such as those caused by big rig trucks, trains, or airplanes. I don't think that any one of those on its own would cause the transformer to vibrate off the pad, but over time you could find...
  10. ogbuehi

    Dual position transformer

    I am working on a project to expand the electrical distribution from a power plant to add a feeder for some loads. I went to the existing electrical distribution to determine configurations and voltages. What I observed on the nameplate of the transformer was something I haven't come across...
  11. ogbuehi

    Electrical inspection

    I've recently taken over a position for someone who has left. We are required to do random inspections on electrial panels installed and maintained by a contractor. I've been reading through past reports and saw a discrepancy that was noted for a particular panel. It stated that unlocked...
  12. ogbuehi

    Trying to size cable properly

    Thanks for the help 7anoter4. Where did you get the thermal resistance for XLPE? Also do you know where to find the temperature rating for XLPE? Thanks.
  13. ogbuehi

    Trying to size cable properly

    These particular cables will be feeding mostly linear loads. Not very much 3rd, 6th, etc.. or higher harmonics. There is supposed to be 2 battery chargers for forklifts when the building is built, but the biggest impact load are motors for some water pumps.
  14. ogbuehi

    Trying to size cable properly

    First of all, thanks for the help. I was thinking the same thing since even though the neutral is treated as a current carrying conductor there shouldn't be much current on the neutral to make much of a difference in regards to temperature considerations. I wouldn't be surprised if it isn't UL...
  15. ogbuehi

    Trying to size cable properly

    We have a contractor submitting a cable that he is requesting our approval on. The load is rated for 300A so he submitted submitted a 300mm^2 (1 run, all phases and neutral in one cable). The voltage is 380V. This cable is to be buried directly in earth and concrete-encased in a electrical...
  16. ogbuehi

    Transformer with wierd test results

    This system is definitely not designed for that. It's supposed to just provide three different phases of 240V to ground via a wye connection with the neutral tied to ground. Very simple system. The transformer was put there as a means to reduce the amount of copper needed to make a very long run.
  17. ogbuehi

    Transformer with wierd test results

    Hmmm, interesting because the neutral is grounded. And I'm almost sure that we checked from A to neutral and B to neutral as well. I will double tap though and verify that. It's just a really long story on why it is such a cumbersome task to gain access to this small transformer. Thanks for...
  18. ogbuehi

    Transformer with wierd test results

    We tested a small, 3-phase, dry type, 20kVA transformer that is delta to wye and 1000V/416/240V. We took a multimeter and measured from from Phase A to ground and phase B to ground on the low side and measured 416V. When we measured from phase C to ground we measured 0V. This told me that...
  19. ogbuehi

    Load calculations

    Man I love this forum. You guys are full of great information. That military handbook has great information. To add some more details about the project, the camp is supposed to be powered by the grid. But the grid is so unreliable they are planning to run on prime power most of the time. So...
  20. ogbuehi

    Load calculations

    I think that's what we may wind up doing that. What we're going to do is force the contractor to tell us exactly how he plans to do the load calculations. It makes sense to me that they shouldn't be trying to use the diversity factor to downsize the generator but should be trying to oversize them.
Back
Top