Existing soil is sandy clay loam, rawls rate 0.17
A grassed infiltration basin will be placed in the area, topped with and 4" loam and seed (assume loamy sand rawls rate 2.41)
What rate do you use for drawdown? 0.17 or 2.41? I think the 0.17 but am being told otherwise
I have been told that it is a rule of thumb that the sheet flow area is reduced to approximately 1/3 area when it becomes shallow concentrated flow, therefore to sheet flow velocity should be limited to 33% downstream erosive velocity.
So if max allowable velocity of a thick grass is 6fps, I...
GRB,
Not much. Off the top of my head, the road is 700 ft long. For the first 500 the water shouldn't cross the road at all. The road is pretty much perpendicular to the contours. Then between the 500 and 700 ft points, approx 20000 SF of grassed land is sloped at approx 3% towards the roadand...
The norm is to have a swale on both sides of the road and crown it. What about having the road slope to one side and eliminate one swale. The stormwater from adjacent land would travel over the road before it gets to the swale, not the best idea, but for a small road with "gentle" slope, a...
after doing some reading i think my first approach may be the right one? no need to add another tc for flow from one pond to the next? hydrocad calcs the time to fill up each pond in the routung calcs? no sure. thanks
my question is should the tc be modeled like this? even tho it doesn;t show most hydrologically distand point I feel likt it is modeling the flow throught the swale? now sure. thanks
[/URL]]
Uploaded with ImageShack.us
model a series of check dams as ponds
is it ok to just connect each pond together (see hydrocad model below)? my question is the tc I am using comes from the north west corner and down to the dam when the pond flows through the swale. DO i need to separate these...