I have had great experiences with their support team. They are responsive to emails, will answer the phone and provide any help you need. Technically they are very proficient and can answer any question you have. I would recommend upgrading to the most recent version of the program as well as...
msquared48 - I'll look into TIA 222G.
hokie66 - So ASCE 48-11 rules over ACI 318 in terms of AB design? Even if ACI is used to size the reinforcing steel?
A vendor designed the anchor bolts for a pair of steel transmission poles with the AB (2.25") spacing at 6" center to center. I have another engineer telling me this spacing violates ACI-318 17.7.1 of min 4*da. ASCE 48-11 doesn't provide any guidance on this. I have seen several places where an...
I am looking to get into these fields, to bring additional services to the firm I work at (design pads for substations). Can anyone recommend training/courses/books that would be helpful for a newbie? Also, any industry standard manuals/procedures. Thanks!
I would like to get some clarification on whether to use phase-to-phase voltage or phase-to-ground voltage when calculating clearances described in Table 235-6 of the NESC Code. The table clearly states circuit phase-to-phase voltage in the column headers but the title references Rule 235A which...