Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Search results for query: *

  1. petro84

    Heat Treatment of Pipe after manufacturing

    Also only in DNV-OS-F-101 there is a correction factor named as fabrication factor which for U.O.E is about 0.85 but not in any other standards
  2. petro84

    Heat Treatment of Pipe after manufacturing

    Hi Dear Friends As I know there are several methods for manufacturing longitudinally welded pipe like: U.O.E,U.O.C, continuous forming and Press Brake. All of these methods cause plastic cold forming.In ASME B31.4 it is written it is forbidden to use material with increased yield strength due to...
  3. petro84

    Cut out of welding due to Repair

    Hi I found something reliable in total specification for this type of repair: "For 3 ½ Ni materials, as well as for austeno-ferritic duplex stainless steels, a second repair of the same area on a given weld shall not be permitted: should a defect be repaired on a previously repaired weld area...
  4. petro84

    Cut out of welding due to Repair

    Dear DekDee thanks for your post; Can you please write what CYA stands for? or make a reference to what you declared above. Thanks
  5. petro84

    Cut out of welding due to Repair

    Hi Dear Friends It is mentioned in our welding Specification that after for Example 2 time repair of Piping, New Defect shall be removed by Cut out; this removal shall include HAZ removal. HAZ per some handbook is 2 mm and macroethced of WPQR samples shows discolored part of base metal is...
  6. petro84

    Injection of Soil under Bottom plates of empty tanks for running permanent C.P Systems

    Hi Dear members we have constructed many storage tanks for a refinery plant but due to many problems, their usage will be about at least two years later.Now we want to run cathodic protection system which is a anode wire system considered for usage under operation. Now all tanks are empty and...
  7. petro84

    Clarification on limits of Qualified WPS Per ASME B31.3

    Dear Dekdee Did you mean 12.7 instead 14 mm ? Regards
  8. petro84

    Clarification on limits of Qualified WPS Per ASME B31.3

    Dear Dekdee you say 5.5 mm to 22 mm for non-impact tested applications ?! but you should declare your opinion based on reality and as stated above for thickness greater than 12.7mm impact test is required. Therefore whats your opinion now ? Thanks for following and consideration
  9. petro84

    Clarification on limits of Qualified WPS Per ASME B31.3

    Dear Dekdee if you take a look to table 323.2.2A then you will see that for thickness greater than 12.7 mm Design temperature without impact testing will be bigger than -29[0c] and as our design temperature is -29[0c] then Impact testing is required per Table 323.2.2 cell B-3. therefore testing...
  10. petro84

    Difference between Employer and Owner

    Hi Dear Friends Due to Paragraph 328.2.3 in ASME B31.3 I have these questions: Does Employer refers to Conractors or Sub-contractor and also are employer and owner considered two different parts ? Thanks for your Consideration
  11. petro84

    Clarification on limits of Qualified WPS Per ASME B31.3

    Hi Dear Friends I ask my Question with an Example: Consider that your Design Code for Piping System is ASME B31.3 and Also your material is in curve B;Design temperature is -29[0C]. So it is mandatory to take impact test for thickness greater than 12.7 mm. Now you know for PQRs with test coupon...
  12. petro84

    clarifying an interpretation of ASME B31.3 about welding

    correction: Y2t to t + Y. in shall be replaced by T/2 to T+6.4 mm s/8 shall be replaced by 5/8 inch
  13. petro84

    clarifying an interpretation of ASME B31.3 about welding

    Dear metenger Iam speeking about range of Qualification for Welding Procedure specification. Our welding Process is Short circuit GMAW and impact test is required. As you know and stated in QW-403.10 in Qualifying a PWPS for short circuit GMAW, the qualified thickness of base metal is up to 1.1...
  14. petro84

    clarifying an interpretation of ASME B31.3 about welding

    hi every body I have a question about following interpretation of ASME B31.3 Interpretation: 15-23 Subject: ASME B31.3-1996 Edition, Table 323.3.1, Impact Testing Requirements for Metals Date Issued: October 30, 1996 File: B31-96-044 Question: In accordance with ASME B31.3-1996 Edition, when...
  15. petro84

    tie- in joint in piping system

    Thanks great guys I always says to managers do not ask me what will happen if we neglect a clause of a standard, because I don't know what was discussed in relevant committees and which aspects were considered, but here I should be directed to a conclusion which was made by Pennpiper. All you...
  16. petro84

    tie- in joint in piping system

    hi everybody I work an inspector of construction project of a refinery plant.Due to wrong ETA(Estimated Time Arrival) of piping components; shortage of material in stock is going to make unacceptable delay in time schedule of construction plan, therefore managers are going to increase the number...
  17. petro84

    In-dependency of QC department from executive departmnet

    Dear friends I work in QA/QC Department for client in a project of constructing a Refinery Plant. Our main contractor Hydro-test Group is going to be eliminated and their members will be distributed in different work areas under supervision of Area Manager. Area managers biggest concern is...
  18. petro84

    auotmated and semi-automated Phase array technique

    Hi every body We want to use Phase array UT in lieu of RT. therefore we shall consider requirements of Code Case 181-2. Iam confused with a phrase stated in Code case 181-2, 1-a), it says:((The examination shall be conducted using automated or semi-automated techniques utilizing computer based...
  19. petro84

    service design factor

    Hi I want to design a piping system by using RTR material based on astm D2996, designing code is ASME b31.3 and my problem is to define service design factor which is used in euation no.26b in paragraph A304.1.2.b. limitation on service design factor was described in paragraph A302.3.2.c but as...
Back
Top