Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. eatapeach

    Puddle welds on roof metal decking

    I am performing observations of the metal decking before the insulation boards are installed, and the contractor performing the welds to the deck is burning a lot of holes through the deck, mostly the size of a dime except a few, maybe the size of a nickel. I typically don't see this many; it's...
  2. eatapeach

    Open Garage Damp Location?

    Would the boxes for the surface-mounted receptacles in a 10-story open commercial garage need to be damp-proof? A hard rain may get some of the boxes at the perimeter wet, but a typical rainstorm would not reach them.
  3. eatapeach

    Water in electrical boxes at garage

    I have an open garage, and where the electrical boxes are located to provide power to the exit lights during rain, water is visible from the boxes. The International Building Code doesn't require a barrier to be provided on the top garage floor, so I would like to know if anything in the NEC...
  4. eatapeach

    Aggregate size in relationship to reinforcement clearance

    I have been searching for the aggregate gravel size in relation to reinforcement clearance. I remember reading once that the reinforcement clearance could not be less than 1.5 the aggregate size. In other words, if the aggregate was 1", the clearance had to be a minimum of 1 1/2". I thought this...
  5. eatapeach

    Concrete cover for Tilt Wall

    Per ACI 318-19, concrete cover for a wall exposed to weather is 1 1/2". Would not a tilt wall be considered exposed to weather? The engineer shows 3/4" coverage over the reinforcement.
  6. eatapeach

    Access to Emergency VFD

    The access in front is not what I questioning. I don’t think you should have to climb over pipe to get to an emergency panel. I mean technically I could fail it based on the International Building Code which requires clear access for a path of egress.
  7. eatapeach

    Access to Emergency VFD

    The electrical contractor installed a VFD exactly as shown on the drawings; however, the only access to it would be to climb over some pipe. It doesn't make sense that you would not have easier access to this variable frequency drive. Does code address access other than clearance to a panel? See...
  8. eatapeach

    Ground Rod

    Very good advice. Thank you!
  9. eatapeach

    Ground Rod

    I am often challenged by contractors when I ask for documentation of ground testing of their grounding system or in today's case, a ground rod. I show up for a final electrical inspection and find the ground rod has been installed however, I have no proof that 3' wasn't cut off (which has...
  10. eatapeach

    Sprinkler requirements for attic

    The design professional used 13, and yes, the contractor wanted to fill it with non-com insulation. It's an R-2 4 stories he could have designed it to 13R but I am not sure why he used 13 other than he just wanted to use the more stringent. Fir blocking every 1000 sq. ft has been installed on...
  11. eatapeach

    Sprinkler requirements for attic

    NFPA states sprinklers are not required in concealed spaces filled with noncombustible insulation. I have an 18" attic/concealed space above the top floor (flat roof), so can I say this is a concealed space? or is it the attic, which I may not be exempt?
  12. eatapeach

    Does anyone know where I could find

    Does anyone know where I could find the backup to require the contractor to isolate the unistrut support from the mechanical duct resting on it? I have read this somewhere in a code or manufacturer product data. I am in the USA under the 2021 ICC codes. Section 603.12 kinda supports it but I was...
  13. eatapeach

    Steel Gas Piping

    The 4” gas line is upstream from the meter and is installed overhead for a cooling tower. The code that I read did state the reason is so someone doesn’t mistaken it for something else. I just do not remember where this was called out
  14. eatapeach

    Steel Gas Piping

    I read in a code but do not remember where but when two or more black steel pipes are installed at the same location, the gas pipe is required to be identified with yellow stripping or painted yellow. Does anyone know where this may have come from? I am in Texas, and I have looked in the 2021...
  15. eatapeach

    Garage / Business

    I have a 12-story open garage with retail stores beneath on the 1st floor. Waterproofing was shown to be on level 2 of the garage however, it got a valve engineered out. Is there anywhere in the code that would require the 2nd floor, which is the roof of the retail space, to be watertight? The...
  16. eatapeach

    When is Expansion required?

    Thanks, I have moved it to structural.
  17. eatapeach

    Through bolt support at Double Tee

    Thanks for the infomation
  18. eatapeach

    When is Expansion required?

    I am inspecting a large garage that is 1/2 precast and 1/2 cast in place. Where the expansion occurs between the two garages I'm trying to locate in code the requirements for piping passing through this location. Would all pipes require some type of expansion or pipe of a certain size? Is this...
  19. eatapeach

    Through bolt support at Double Tee

    Is there a location on a Double Tee where you should not have a through penetration for a 3/4" bolt being installed to support piping? I am inspecting some 12" Chiller pipe being supported from each Double Tee in a garage. The contractor has drill holes for two supports approx. 4" down from the...

Part and Inventory Search