Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Search results for query: *

  1. SperlingPE

    GPR & x-ray concrete

    How good is ground penetrating radar? Can it detect reinforcing size? Typical situation, CIP building with no drawings of information on reinforcing. Is x-ray the better way to go to find reinforcing sizes?
  2. SperlingPE

    Concrete Accelerator

    I appreciate the information. This is a CM project. The wall is 150' long, 14' high, and 18" thick. I'd like to hear about any issues to be concerned with using an accelerator. The goal here is to be able to back fill sooner than 28 days. I know strength will likely be achieved in 5-10 days...
  3. SperlingPE

    Concrete Accelerator

    I am aware of the chloride based accelerators and the effect on reinforcing. I can't recall ever using an accelerator in a cast wall situation. good idea? bad idea? what should I look out for?
  4. SperlingPE

    Concrete Accelerator

    What do I need to be aware of if accelerator is used for a concrete wall? Accelerator is being considered to be able to backfill sooner. It is an 18" thick, 14' tall foundation wall. It will be supporting first floor framing and have some columns bearing on it.
  5. SperlingPE

    Design of Below Hook Lifting Devices

    Thanks all for the information. I have now seen all the devices. The majority of them are steel tube spreader beams. There are a few yoke plates. There are some welded up bolt on lifting devices. The heaviest load is less than 2 tons. I am looking for a resource for design of spreader beams.
  6. SperlingPE

    Design of Below Hook Lifting Devices

    Without details, that is where the load test comes in. Does the thought process sound right or do the pieces need to be tested to failure?
  7. SperlingPE

    Design of Below Hook Lifting Devices

    These lifting devices were made in the shop of our client. No drawings exist of the devices [same old story, been used for years]. Some of these lend themselves to be able to calc a safe load rating. Others do not [odd plate shapes, unknown weld sizes, etc.]
  8. SperlingPE

    Design of Below Hook Lifting Devices

    Good day, is there a specification or design guide for designing below hook lifting devices? A client has several in house made lifting devices that they would like to get a load rating on. Our thoughts are to do calc's if possible and apply appropriate safety factors. So I am trying to find any...
  9. SperlingPE

    Mis-placed anchor rods

    Hilti rep referenced some testing done in the 80's [no link provided] with abandoned holes and wedge anchors. The response did not address my specific situation with an abandoned cast in anchor. I am waiting on additional information.
  10. SperlingPE

    Mis-placed anchor rods

    I have been in touch with Hilti rep.
  11. SperlingPE

    Mis-placed anchor rods

    1" rods cut off new 1" post installed anchors 2" away center to center distances
  12. SperlingPE

    Mis-placed anchor rods

    If anchor rods are mis-placed by inches, can post installed anchors be installed adjacent to the cut off anchors? My thought is that the cut off anchors would be like a piece of rebar in the footing. I should say that there is tension on the new post installed anchors. The cut off anchors would...
  13. SperlingPE

    Anchor Rod Placement

    The anchor rods for a PEMB project were placed in one of the following ways: 1. Concrete for the pad footing was placed, the anchor rods were pushed into the concrete, the concrete was consolidated. 2. Concrete for the pad footing was placed, the concrete was consolidated, the anchor rods were...
  14. SperlingPE

    Risk Category IV wind speeds v. tornado wind speeds

    Thanks all. Wind gusts and tornado winds are different animals and this was explained to the client. They asked for a study after hearing our explanation. Do the FEMA documents use the Fujita scale for the wind speeds? This is strictly a study at this time. The missiles and internal pressures...
  15. SperlingPE

    Risk Category IV wind speeds v. tornado wind speeds

    A client is asking us to evaluate the differences in structure due to the wind loads from typical risk category IV wind speeds [120 mph] and an F2 tornado highest value wind speed [157 mph]. I explained that these are two different things (3 second gust and a possibly longer sustained wind...
  16. SperlingPE

    Concrete Shrinkage in Footings

    The shrinkage will also depend upon humidity and other conditions that cannot be controlled. I have been searching for any type of information. Most information found has to do with slabs and does not address possible vertical shrinkage.
  17. SperlingPE

    Concrete Shrinkage in Footings

    rapt - how did you come up with your number? The soils engineers are working on values for input into FEA mat slab foundation design.
  18. SperlingPE

    Concrete Shrinkage in Footings

    leveling of the machine is not an issue this can be done when the equipment is set the issue is what can be expected for concrete shrinkage in the first nine months after the equipment is set? this also can be taken up by the machine, but the supplier would like to know what kind of number to...
  19. SperlingPE

    Concrete Shrinkage in Footings

    Plates and leveling rods are being used to level the embedment bars in the concrete. The embedment bars are attached to the plates and leveled. Non-shrink grout is then poured around the embedment bars. This covers the plates at this point. Shrinkage can be dealt with when the equipment is...
  20. SperlingPE

    Concrete Shrinkage in Footings

    Some background. New sensitive equipment installation. The foundation will be poured and the equipment will be installed 90 days later to take care of the majority of any possible change in volume. The new equipment is sensitive to height differences where it interfaces with the foundation...
Back
Top