Dear Mr.fegenbush
Yes it is constructed to ASME Section VIII Division 2
The contractor is insisting on having UT instead of RT , I went through the standard and I was confused of categories ..so I asked for help.
By the way ...I didn't understand what you've written: These projects are quite...
Hi
Thanks for your answer....actually the spherical tank is shown in the attached filehttp://files.engineering.com/getfile.aspx?folder=60d12fe9-ef30-4602-b225-030728ec7c50&file=download_(4).jpg
Hello
Can you tell me please if is it OK to exam the tanks'welds by Ultrasonic method and not with radiographic method???
The tanks are 1000 -3000 m3 LPG Spherical .
Thanks in advance
The problem is that we have large petroleum tanks ( 15000 -50000 ) cubic meter capacity
some tanks'shells are damaged ( corrosion , bullets ...) ,the tanks are in service and we have to repair the damaged shell !!!!!
I read about a material ( paste ) that can be but on the hole and it fill...
Dear sirs,
I don't understand the following paragraph from API 650 - section 5-Design - 5.1.5.2 Vertical Shell Joints:
b. Vertical joints in adjacent shell courses shall not be aligned, but shall be offset from each other a minimum distance of 5t,
where t is the plate thickness of the thicker...