Hello,
Some capital projects asks for design reviews in 30%, 60%, 90&, 100% while others asks for 50% and 100% only.
what is the difference and when we follow option 1 and when is 2?
thank you
Hello,
I am looking for reports, or schedules which describe all the info and codes, tests required to install all finishes and how to supervise it
ex: Epoxy: need to be mixed with water not more than 2 hours, where to put, how? recycle content, free VOC & formaldehyde
Wooden cabinets: need to...
Thank you bridgebuster for your help, No not the MSDS, MSS?
what is reffering to , I saw it review MSS, SD, RFC
I know SD shop drawings
rfc request for clarification but what is MSS?
Dear All,
As I am a beginner, I wish to guide me see how any projects constructor step by step, hope by images or video.
I am looking forward to see all details on site, like pouring concrete, mock-up tests, rebar coupled, concrete casting, slab installing and further more .
Any recommendations?
Dear all,
I am new engineer in company, we are the client or the owner for a project, so we are manage the construction with contractor,
I am an architect with little experience, I need to do a work which realy be appreciated and shown.
My scope now to review subbmittals, modify some work...
Hello,
I got shop drawings subimttal for the Lapeyre stairs attached with the original specs as providing the stair manufacturers, specs, material.
The drawings it self is correct but they did not attach the manufacture, quantities, or any specs for the material the chose.
They mentioned in the...
Hello,
I got shop drawings subimttal for the Lapeyre stairs attached with the original specs as providing the stair manufacturers, specs, material.
The drawings it self is correct but they did not attach the manufacture, quantities, or any specs for the material the chose.
They mentioned in the...
Yes, I am an architect,and asking for the architectural composite plans and roof , I just joined that project , I am the only architect and need help ti know the important things I need to look at in term of reviewing shop drawings and approve submittals.
Many thanks for your responses[highlight #FCE94F][/highlight].
The problem that I am the only architect on this project, it is new and I have received the first submittal.
So, for me there is no reference as an architect discipline and I have never done any submittal before. Ok is there some...
Thank you for your response.
I may not make it clear.
as it is the first time for me, the contractor send his submittal attached with the shop drawing for the roof and mezzanine plans.
My question is: How I can look to the drawing to see any thing missing or need to be resubmit.
I took a copy...
Hello,
This is the first time for me to review submittals, Architecture
Wee have to review two submittal one for mezzanine composite plan, now i am looking in the IFC and Shop drawings, what I supposed to catch if there is any comments?
The other one to review for the roof composite plan...