  1. juststo

    Month end total

    I am using project and trying to sum figures in a column to get a month end total. Is there any way to calculate a number of tasks vertically in project?
  2. juststo

    Can MS Project do this???

    Could I solve this problem in Excel and then import it into Project? I'm using the demo now and want to know if I should buy. What exactly are the strengths of project? I have looked at other forums and there are questions like mine. It seems reasonable to have your scheduling software...
  3. juststo

    Can MS Project do this???

    I run a wood working manufacturing company. I am having difficulty getting Project to do what I need. Here is my example. I need to cut 400 boards. I have a saw (resource) that can cut 10 boards an hour. I want to be able to put in this rate and have Project tell me that this task will...