Hi
I got it; Now I am using "Customize Assignment" Screen ;
If the Weekly meeting lasts one hr,
I am entering as follows for each Meeting1 , Meeting 2 :
Task Type = Fixed Work
Resource % Work
Name1 100 1 h
Name2 100 1 h
It is OK now
Thanks
Hi All,
I have assigned Work hrs to the Sub-tasks; It adds up as the Work Hours for the Parent Task (e.g. Meetings)
When I assign Resources to the Iterative Task, it messes up the Total Work hrs for the Parent;
I am doing anything wrong while assigning the resources for the Meeting?
Thanks